Getting close to moving back in

Image
Here is a walk-through video of where the progress is today. Most of the plumbing and framing is done. HVAC is in progress - the furnace is back in. Electrical is hooked up. https://youtube.com/shorts/Jth1b_Yju9w?si=eVaYDkll8FSI6BQU

More electrical, beam pockets filled, and egress windows

Image
On Wednesday, they completed the rest of the electrical work (enough to get us reconnected and back in the house - we don't have light switches, etc in the basement yet.). I also drove my dad to Kearney after his graduation/release from Madonna Rehab Hospital. He has come along way, and we're glad he was able to leave Madonna.  They had to trench and lay new electrical.  We had the beam pockets filled in on Thursday. And egress windows installed on Friday.  Our general contractor also came Friday afternoon to backfill some of the dirt to prepare for next week. Hopefully we have stairs and walls, HVAC, and plumbing hooked up next week after Christmas! 

Electrical and concrete

Image
We expected the concrete on Friday, because they did all the prep on Thursday, but it was just too rainy and wet.  So, the electricians came and installed the new electrical panel. I do not think it is trenched into the electrical box yet, so that will come later.  Then the concrete crew (10+ guys) came on Monday (today)! For a 1 min 30 sec video compilation go here:  https://youtu.be/NXPAWfTV9lA?si=9740q5xIQltsrdAx They came around 8am and were done for today by 2pm. It was really great to watch. Check out the linked video for some video clips of them working.  https://youtu.be/NXPAWfTV9lA?si=9740q5xIQltsrdAx