House lowering video

Image
When I posted pictures on November 20th of the house being lowered, I didn't post any videos. So here they are! https://youtu.be/bEszEfy75Vk?si=KAHZshDjlnhTPDD3 I also went back and added this video to that original post, so I could preserve it there, too. 

Update - end of January

Image
As posted previously, we got back into our house on January 5th - right before snow and really cold temperatures. The Lord really protected us while we were living in the camper with mostly mild weather.  Here's an updated video walkthrough of the basement: https://youtu.be/aX4EeGvGkec?si=6CN2G7DGYUwL3Raf And here are a few pictures: Larger bedroom. This opening will be a closet. Bathroom Living room Smaller bedroom Storm shelter Utility room Utility room Electricians came last week to install electrical on our half bath and stairwell. Half bath Where the vanity will go Where the toilet will go.  ----- We are still waiting on HVAC before we can close up the walls where the chimney was removed. We also are using electric heaters in our bathroom, living room, and bedrooms. The furnace is running, but we don't have ductwork yet.  Opening where the chimney used to be. Open between dining room, living room,  and guest room. 

Got back in!

Image
We slept in our house for the first time in 106 days on Friday (Jan 5th)! The workers were here until 6:45pm that night, so we'd have running water, propane to our stove, and the essentials! The ductwork is yet to come and we have a lot to get clean and put away, but we're thrilled to have more room and security from the weather! 

Waiting on well and HVAC

Image
Before doing this project, I really had no idea how many things needed to happen before we were back in the house. We are currently waiting on our well pressure tank to be hooked up and the HVAC ductwork. The water heater is installed and all the plumbing is pretty much ready. But until the pressure tank is hooked up, no water can flow from the well to the house. Praying that it happens today.  We could get back in even if the ductwork isn't complete, but without running water, we might as well stay in the camper. The weather forecast for next week looks pretty cold and snowy, so really praying a lot of progress happens today.  Here are photos of work that has happened over the last week.  We have some lights! Eventually we'll add can lights, outlets, etc.  The half bath off out guest bedroom is framed, insulated, and plumbed.  Furnace is in and running, but no ductwork yet.  June helped pick out floor tile for the half bath.  The vanity for the half b...